Regional district's downtown office heating fix now pegged at $663,800 to tie into the city's wood-waste energy system
Fraser-Fort George directors again held off on choosing between the city's district energy system and electric boilers, and want to know first how long the wood waste will last.
By The PG Current newsroom

The Regional District of Fraser-Fort George still has not decided how to replace the failing heating system at its administration building at 155 George St. in downtown Prince George, after directors received updated prices at the new board's first meeting on Nov. 19.
The building's heating has been running short of capacity since a boiler failed in late 2022. In May, the board told staff to negotiate a connection to the City of Prince George's Downtown Renewable Energy System, which burns sawmill residue at Lakeland Mills to heat water that is piped to buildings in the downtown core. In September, the estimate for that hookup was $611,300 in one-time charges, and the board postponed a decision 7-6 because some directors were uneasy about the numbers.
The new report puts the payment to the city at $663,800, plus about $107,000 in work inside the building to get it ready. The alternative, two electric boilers, would cost about $312,700 plus GST to install, but staff said the boilers would use 408 of the building's 417 kilowatts of electrical service. Because the building's standby generator produces only about 230 kilowatts, keeping the heat on in an outage would mean new generating equipment estimated at $450,000 to $800,000. Over 20 years, staff estimate net costs of about $1.2 million for the district energy connection and $1.6 million for electric boilers, with similar emissions.
Robson Valley-Canoe director Dannielle Alan asked what would back up the system if the wood waste ran out. The city's supply agreement with Lakeland Mills, renewed in 2025, runs to Dec. 31, 2026, with optional one-year renewals for 2027 and 2028, and the city keeps natural gas boilers as backup. Prince George Mayor Garth Frizzell moved to ask the city for a report on its long-term fibre supply commitments, which passed unanimously. Chief administrative officer Chris Calder said staff would try to have it before the next board meeting on Dec. 10.
What it means for Prince George and regional taxpayers: The regional district's office costs are shared by property owners across its member municipalities and electoral areas, so the option the board picks will show up in its 2027 budget. Each month without a decision leaves staff working in a building that is heated at partial capacity. For the city, a new paying customer on the downtown system would add to the revenue that supports it, but only if the wood-waste supply behind it holds.
Sources: Prince George Citizen, Regional District of Fraser-Fort George, Nov. 19, 2026 board agenda, City of Prince George, Downtown Renewable Energy System.